This topic will cover how to update the work breakdown structure for an existing project. The work breakdown tab is used to define what the target budget is for each sub project, by adding a budget entry for each sub project, task, rate, or staff member. NEW 4.8
*Synergy Enterprise Feature*
Setup required before use |
Who can use it? | Where is it? |
---|---|---|
Assistant Project Manager Project Manager Director Administrator System Administrator |
Projects > Project Plan > Work Breakdown |
Tips:
Update the Work Breakdown structure when new project tasks have been identified and need to be added to a sub project, or existing tasks need to be removed. Update the work breakdown structure to reflect the new budget for each sub project, based on the required work. Add the staff members to the sub project tasks, once it has been decided who can complete the work. The work breakdown structure is part of the Resource and Capacity Planning module. NEW 4.8
Add or update items within the Work Breakdown structure tab when the Sub Projects are at any status. The work breakdown structure can be updated with the sub project status of Proposal or Active.
Add additional tasks to the work breakdown tab if extra work is identified as required for the sub project. Learn how to create new work breakdown items in the creating the work breakdown structure topic.
Update the details of a work breakdown row, to change the value of the budget for the sub project. To edit the item:
Tips:
The Staff drop down shows the staff who are setup to use the chosen rate, and work within the project office. If Project Teams is enabled, then only staff listed on the Project > Team tab are shown.
Use the copy feature in an open work breakdown item to copy the same task to be used multiple times within a sub project. This is useful when you want to assign the same task to different staff members.
Tip: Copy items within the same sub project only.
Budget templates can be setup in Synergy with the standard staff, inspection or expenses required to complete a certain task. i.e. Budget templates maybe created for building a school hall, or for building a townhouse etc with the standard items quoted for that style of work. Add a budget template to the work breakdown structure for your project using the Copy button in the top toolbar. The Copy button can be used once the Sub Project row that you want to add the items to has been selected in the list.
Markup the budget template values if this sub project will be double or triple the value of the template. A custom markup value can also be entered. Using the toolbar the budget template items can be marked up from the original template entered units / value. Use the factor options of 'x 0.5' or 'x 2' or 'x 10'., or enter a custom markup value by typing the value into the custom field in the toolbar. The markup value selected will multiply the template values by the selected amount. i.e. 'x 2' markup value will multiple the Units/ Value of the budget template by 2.
Copy work breakdown items from a budget template by:
Tips:
Update the budget values to reflect the real rates that you plan to use for invoicing for a project. Add project or sub project level specific rates to the project, then use the 'refresh budget' button in the work breakdown tab to apply the updates rates to the sub projects.
Step by step instructions on this feature are available in the Work Breakdown overview topic.
Use this feature to remove a work breakdown item from a Sub Project.
After updating a rate to have a new rate value in Practice > Rates List, the item in the work breakdown budget is not automatically updated. This is because the sub project fees were already created using the existing budget values entered. However it may be relevant to update the sub project budgets to display the updated rate.
Tips:
Use the mark as complete feature to stop users from being able to select the task when entering timesheets.
Click the image to see the percent complete entered for each WBS task.
Tips: