Update the Project Planning Board when the date/time of the work breakdown item has changed to, or to assign a different staff member to complete the work. NEW 4.8
*Synergy Enterprise Feature*
Setup required before use |
Who can use it? | Where is it? |
---|---|---|
Assistant Project Manager Project Manager Director Administrator System Administrator |
Projects > Project Plan > Schedule > Planning Board tab |
Tips:
Update the Project Planning Board when:
Tip: Adding a staff member to the scheduled task, shows the task in their My Schedule plugin on the My Synergy dashboard, and displays the task in their timesheet history on the scheduled date.
The delete option can be used if the appointment has been scheduled on the wrong date, or if the project work for the task is no longer required.
To delete a scheduled item:
Tip: Delete is allowed for all scheduled items. Whether the item is marked as complete, or if transactions have been allocated to the item via staff timesheet entry.
Edit an appointment to change which staff member is allocated to complete a task, or change the length of the appointment.
Double click an appointment item in the planning board, and the edit appointment window opens. The edit appointment window allows you to change:
The appointment for Robert Howard's site inspection has been added to the project. The task was initially scheduled for October, however Robert was not able to complete this work. Edit the appointment to re-schedule Robert to complete the task.
Complete the following steps:
Click the image above to view the start time of the appointment being updated.
After checking the Project Capacity Board, the staff member assigned to the task is not available to complete the work. The appointment in the planning board needs to be updated to a staff member that is available.
Complete the following steps:
When planning an appointment the default scheduled hours total used is based on the office/staff calendar settings. This means that if you have set the start / end time of the appointment to be greater than those hours, only the max office hours is shown as the total scheduled time for the appointment in the capacity report. Uncheck the 'Use working hours to calculate capacity' box on a planning board appointment if you want to plan a staff member to work overtime, or outside normal office hours on weekends.
Example: Robert Howard is planning to work extra hours on a project task to meet a deadline. He will be working an 11 hour day to complete the Design work. The normal office hours are set to 8 hours. Unchecking the working hours box on the appointment will show that Robert will work 11 hours instead of 8 hours on this date.
Change the appointment to use working hours by:
Click the image above to view the check box on the appointment for scheduled vs working hours.
Click the image above to see the appointment on capacity board using scheduled hours.
Tip: Uncheck the working hours box to plan staff members to work on weekends, and have that task show in the My Schedule plugin and timesheet history for that staff member.
Other tips that make updating the Planning Board easier:
In the planning board hover the mouse over a scheduled item, and more details are shown.
The details shown in the hover box are:
Click the image above to view the task hover box. The hover is shown over the 'Report' task scheduled.
The Projects to Schedule panel displays the columns Budgeted and Scheduled next to each Work Breakdown item. This allows you to view the number of units entered in the work breakdown structure. Use these fields as a visual check that an item is not over-scheduled on the planning board, to attempt to keep the Project Budget on-track.
Click the image above to see an item which is over scheduled, where more hours in schedule than were in the budget.
© 2019 Total Synergy Pty Ltd