Setup required before use |
Who can use it? | Where is it? |
---|---|---|
Assistant project manager Project Manager Director Administrator System Administrator |
Project > Forecast tab |
The Project Forecast builds upon the Agreed fee and Budget data entered against Sub Projects to build a future cash flow budget based upon the sum of individual project plans. The Cash flow budget can be augmented by predicting cash flow for jobs that are in submission with the cash value depreciated by an expected success factor providing a pipeline cash forecast. The combination of the won project cash flow and the pipeline cash flow provide a total cash flow forecast for the practice. On the Forecast tab, view a Summary of the forecast values in both the list and chart views.
Synergy Project Forecasting provides for an initial forecast to be developed and captured as a baseline forecast which may then be contrasted with the ongoing rolling forecast.
Use the forecast tab to check on the progress of one or all Sub Projects. Compare the planned forecast revenue values (baseline) against what was actually invoiced. Know what Sub Projects to follow-up with the staff about, to see why the forecast revenue does not match what was invoiced.
Use forecast list to review the forecast values for each of the Sub Projects. Monitor the residual forecast values using the colour coding (red / blue) to see what values need to be adjusted in the forecast. The forecast displays a monthly breakdown of values for the next 12 months, and the 12+ month column contains a sum of any other future months forecast values.
Click the list above to view the forecast values for a project.
Notice the residual values are shown in blue, as the forecast fee has not been entirely allocated for those Sub Projects.
Tips:
Use the forecast chart to see at a glance how each Project or Sub Project is performing. Compare the baseline forecast value (planned revenue targets), with the rolling month updated forecast values (current forecast values) and the invoiced values (charged value).
Example
The example below displays a single Sub Project. The Baseline values were set for the initial sub project forecast of 10 months (shown in green). The sub project work was later delayed, which resulted in the forecast revenue being adjusted to be split over 12 months instead (shown in blue). This can be seen by comparing the baseline and forecast values below.
The work for August and September was completed ahead of the planned schedule. This resulted in a higher invoice value for August, and a lower value in September (shown in pink).
Click on this image to view the chart which displays the forecast, baseline, and the invoiced values for the selected Sub Project.
Click 'Hide Chart' to turn off the forecast chart display. Useful if you have a large number of Sub Projects you want to review in the list.
Select the 'All Sub Projects' button which is located above the graph. The forecast chart will then display the monthly total values (SUM) for all Sub Projects. The Forecast, Baseline, and Invoiced values are shown for all sub projects.
Select 'Selected sub project' in the Graph table, which is located above the graph. Choose which Sub Project values are displayed, by selecting it from the list. The Forecast, Baseline, and Invoiced values are shown for the selected sub project.
Tip: This tab will remain with the 'Selected Sub Project' setting until the 'All Sub Projects' is selected again. This means you can continue selecting each different sub project in the list, without changing this setting each time.
The following reports are available for download from the Synergy online library, to use for Project Forecasting Reporting. NEW 4.8
Report Category | Report Title |
---|---|
Project |
Project Revenue Forecast + Reports the forecast values for all projects in Synergy, displaying a monthly breakdown for the first 12 months, and a 13 month+ column to display the forecast for anything greater than 12 months out. Proposal Success Factors adjustments are applied to the values in this report when the project is at Proposal status. Project Revenue Forecast + (No Adjustments) As above but Proposal Success Factors adjustments are not applied to the values in this report.
Try adding the following report filters: "Project Manager IS David Choice" to display all the forecast values for David's projects. 'Project Office Name IS SYDNEY" to display all forecast values for projects linked to the Sydney office. |
Sub Project |
Sub Project Revenue Forecast + View a breakdown of the forecast values by sub project, over a 12 month period. Use the 13+ months column to see any forecast values scheduled for greater than 12+months out. Proposal Success Factor adjustments are applied to the values in this report when the project / sub project is at proposal status. Sub Project Revenue Forecast + (No Adjustments) As above but Proposal Success factor adjustments are not applied to the values in this report.
Try adding the following report filters: "Project Reference Name IS Australia Golf Club" to view the forecast values for only the Australian Golf Club project. "Project Manager IS David Choice" to display all the forecast values for David's projects. 'Project Office Name IS SYDNEY" to display all forecast values for projects linked to the Sydney office. |
Tips:
Looking for more help? Try reviewing the following Projects topics: View Topics
Or try the following Forecasting topics: View Topics
© 2019 Total Synergy Pty Ltd