The invoice is marked as paid in full in Synergy and the accounting package. Changes now need to be made to the invoice. This requires that the invoice payment is removed and a new invoice is created. The creation process in this topic shows you how to complete the invoice re-creation process keeping the same invoice number, when the invoice is shown as paid in full.
Setup required before use |
Who Can Use It? | Where Is It? |
---|---|---|
Project manager Director Administrator System Administrator |
Projects > Invoices tab |
I need to redo an invoice for a client and use the same invoice number. The original invoice is in my accounting system and has been paid. What do I need to do?
There are several steps in this process that need to be followed to ensure that values in Synergy and your accounting system balance. The steps below will also make sure that you don't end up with duplicate entries in your accounting package (items are not resent).
Tip: The steps outlined below show how to complete this process where Xero is your accounting system. The steps are very similar in other accounting systems.
A past invoice requires amendment. The invoice should have only listed the sub projects that included an invoice value, and the invoice period was set incorrectly. The invoice in Synergy and the accounting system is already shown as paid in full.
Click the image above to view the invoice that is paid in full.
The invoice was created last year in Synergy and sent to Xero using Synergy Connect for Xero. The payment was received for this invoice and applied in your accounting system. Synergy Connect for Xero was run again and the payment was imported into Synergy and allocated to the invoice.
The invoice now requires amendment and the updated invoice needs to use the same invoice number.
First we need to remove the invoice payment from Synergy and the accounting system. After the payment has been removed, we can then cancel the Synergy invoice and sync the credit note to the accounting system. The credit note is then applied to the invoice in the accounting system.
In this step we need to update the existing Synergy and Xero invoices to have a different invoice number. After the invoice number has been changed on the existing incorrect invoice, we can then create the new invoice in Synergy. The new invoice in Synergy can then be updated to have the original invoice number. The new invoice is then sent to Xero using Synergy Connect.
Note: In Xero you must void the credit note to change the invoice number, and then apply a new manual credit note to the original invoice in Xero. This is not required in MYOB V19.9 as you can change the invoice number even if a credit note has been applied. Each accounting system works differently for this process. If you are not sure how to do this please contact support.
The re-created invoice now needs to be set as paid in both the accounting system and Synergy. After sending the payment to Synergy using Connect, we then need to alter the Synergy Connect 'Export date' settings back to the current period. This is to prevent older data from Synergy being sent to the accounting package for a 'locked' or 'completed' period.