Enter exception days for things like public holidays and builders RDO’s. You can also create your own calendars that may be specific to certain builders or states.
Calendars are used when calculating a new practical completion date due to an Adjustment of time (AOT) and when calculating the expiry of the Defects Liability Period. Exception and non working days are skipped when calculating the new dates.
Setup required before use | Who Can Use It? | Where Is It? |
---|---|---|
Project manager Director Administrator System Administrator |
Contract Admin > Contract Default Data > Calendars |
Tips:
Exception days are used to mark which days are not to be counted as working days. Most commonly used to record builder’s RDO’s, picnic days and public holidays.