Progress claims are used to assess and maintain the contractor’s claims for work which has been completed to date. Each claim is allocated an automatically generated claim number. Where the original contract sum is a single fixed value, each claim is expressed as a single amount claimed against the contract as a whole. Where the original contract sum uses a breakdown, each claim contains a breakdown assessment. The total claim amount is made up of individual claim amounts against each item.
Tips:
Tip: If one or more claims have been certified with a progress payment certificate, the cancellation will fail. All claims being cancelled must be uncertified .
Looking for more help? Try reviewing the following topics: View Topics
© 2019 Total Synergy Pty Ltd