Progress claims are used to assess and maintain the contractor’s claims for work which has been completed to date. Each claim is allocated an automatically generated claim number. Where the original contract sum is a single fixed value, each claim is expressed as a single amount claimed against the contract as a whole. Where the original contract sum uses a breakdown, each claim contains a breakdown assessment. The total claim amount is made up of individual claim amounts against each item.
Setup required before use |
Who Can Use It? | Where Is It? |
---|---|---|
User Assist. Project Manager Project manager Director Administrator System Administrator |
Contracts > Progress Payments tab |
Tips:
The Progress Payment cannot be created without recording the Contractors Progress Claim. After approving the Progress Claim the certificate can be found on the Progress Payments tab.
The claim will appear as approved though not certified until the Progress Payment is created.
Use these columns to enter the amounts excluding tax claimed by the contractor against each item. The claimed values can be entered as either a dollar value or as a percentage of the Item Amount.
Use these columns to enter the amounts excluding tax that you are approving against each item, either as a dollar value or as a percentage of the Item Amount. Alternatively, if you are approving all or most of the amounts claimed, tick the Approve All button. This will fill in the Approved Amount column with the amounts claimed, you can then make changes to the approved amounts if required.
Clicking this button will reset all columns with blue values back to zero.
Tip: If one or more claims have been certified with a progress payment certificate, the cancellation will fail. All claims being cancelled must be uncertified .
To deduct retention from the claim, tick the Deduct Retention check-box on the form NOTE: The check-box will be disabled if the contract doesn’t use retention for security, or if the contract uses security and has been set to deduct retention automatically from each approved progress claim.
In the event that the retention amount to be deducted for the claim exceeds the maximum retention amount allowed for the contract, the retention amount will be adjusted to reach the limit. No further retention will be withheld from future claims.
The Amount Due is the difference between the total amount approved and the total of the amount of liquidated damages specified and the retention amount (if applicable) retained for the claim.
Looking for more help? Try reviewing the following topics: View Topics
© 2019 Total Synergy Pty Ltd